I read The Oil Drum (TOD) an excellent energy site that openly discusses Peak Oil and related matters. The geeks have kicked in on the website and there is much technical discussion about drilling and this spill. A BOP is a Blow Out Preventer for those of us who don't know...

Comments on Some Recent Oil Spill News Items, Including the Dome
Posted by Heading Out on May 4, 2010 - 11:25am
Topic: Environment/Sustainability
Tags: bp, oil spill [list all tags]

Today, I have just a few comments on recent oil spill news items.

The steel and concrete containment dome that is the first of the three systems that BP hope will be able to cap the leaking riser has been built and will be shipped out today. There are three points at which the riser is leaking oil. The main leak is some 600 ft from the well head apparently. Part of the concern as to how well it will work, even if it does get put in place by the end of the week, lies with the relatively soft seabed at the point where the cap will be placed.

Nate Hagens has a good description of what is intended, showing the plan for capping each leak:
Image from Superior Energy - (via Johnson Rice)

How it works


• The system is made up of a 125-ton, 14’ x 24’ x 40’ structure that will be set on top of the largest leak source. This leak is located at the end of the riser, about 600 feet from the wellhead.

• Equipment at the top of the system is connected to a 5,000 foot riser that will convey the hydrocarbons to the surface ship, the Deepwater Enterprise.

• Once in place, oil will flow up into the containment system’s dome to the surface ship.

• Once on the surface ship, the hydrocarbons will be processed and oil will be separated from water and gas. The oil will then be temporarily stored before being offloaded and shipped to a designated oil terminal onshore.

• The Deepwater Enterprise is capable of processing 15,000 barrels of oil per day and storing 139,000 barrels.

• A support barge will also be deployed with a capacity to store 137,000 barrels of oil.

• This system could collect as much as 85% of oil rising from the seafloor.

There is also a picture of the cap itself, from the same source. While the impact of the spill has not stopped other companies who are drilling in the Gulf. It has caused the Governor of California to shelve plans for off-shore drilling in California, for the present.

The report from a fisherman who was fishing near the rig at the time of the explosion states that the rig first vented water, and then natural gas, and that after the lights on the rig went out. The explosion came possibly as the emergency power generator kicked in.

There has been some significant attention paid as to whether the rig should have been fitted with an acoustic remote control system for the BOPs – though in one discussion I heard there was some confusion as to what this would have changed on the rig, since there were BOPs in place. The acoustic system has the following benefit:

The ACS system is a redundant receiver/transmitter for communication with the rig through acoustics. It is interfaced to the BOP control pod so that different sets of emergency functions can be executed to shut down the well and avoid a pollution. If the regular umbilical is broken and normal communication with the BOP is not possible, the ACS is the last and only means to shut down the well. If a function is executed from the ACS, signal goes to a solenoid that activates a big valve on the BOP; the valve is then energized by air pressure bottles on the BOP.

In this case that doesn’t seem to be likely to have helped, since there was, apparently, a signal on the rig floor that the BOP had activated, though obviously it had not worked the way it was intended. The reason(s) for the BOP failing to work as anticipated is still a matter of conjecture.

42 comments on Comments on Some Recent Oil Spill News Items, Including the Dome
You must log in to post a comment. If you don't have an account, create one.
ShareThis Show without comments PDF version
tollertwins on May 4, 2010 - 10:34am FWIW....found this last nite.....

http://www.northeastshooters.com/vbulletin/showthread.php/99645-Deepwate...

Deepwater Horizon Info
This is from a friend....

> Terry xxxxxxx, who works for ADTI, had a son who was one of the BP Company
> reps on the Horizon when the incident occurred. Here's what he sent me.
>
> TALKED TO MY SON, HE IS AT HOME NOW, AND IN GOOD SHAPE, WHAT I WAS TOLD WAS
> THEY HAD SET A 9-5/8 TAPERED PRODUCTION LINER, DID THEIR CEMENT JOB, HAD
> POSITIVE TESTED, AND ALSO NEGITIVE TESTED, THEY WERE GOING TO SET A BALANCED
> PLUG AROUND 3000' BELOW THE WELL HEAD WHICH WOULD BE AT ABOUT 8000', THE
> SENIOR COMPANY MAN WANTED TO SET THE BALANCED PLUG IN MUD, BUT THE ENGINEERS
> WANTED TO DISPLACE WITH WATER PRIOR TO SETTING BALANCED PLUG, SO THEY
> DISPLACED FROM 3000' BELOW MUD LINE, AND WERE GETTING READY TO SET PLUG. THE
> DERRICKMAN CALLED THE DRILLER AND SAID HE NEEDED HELP, HE HAD MUD GOING
> EVERYWHERE, AND ABOUT THIS TIME THE DRILL FLOOR DISAPEARED, THEN THERE WAS
> AN EXPLOSION, THEN A SECOND EXPLOSION.
>
> THE FLAMES ARE NOW GOING STRAIGHT UP ALLOWING EVACUATION OF MEN, THEN YOU
> KNOW THE REST.
>
> THE HANDS THAT ARE MISSING ARE THE ONES THAT WERE ON THE DRILL FLOOR AND
> PUMP ROOM. YOU KNOW THE RESULTS OF THAT. THIS ALL TOOK PLACE IN LESS THAN A
> MINUTE.
>
> RIG WAS EVACUATED IN ABOUT 25 MINUTES.
>
> IT IS BELIVED THAT THE SEAL ASSEMBLY AT THE WELL HEAD GAVE UP. IF THAT IS
> THE CASE AND THEY WOULD HAVE SET THE BALANCED PLUG IN MUD THEN DISPLACED THE
> RISER, IT WOULD ONLY HAVE DELAYED WHAT HAPPENED BY A COUPLE OF HOURS.
>
> GAS MUST HAVE CHANNELLED THROUGH THE CEMENT JOB AND UP THE BACK SIDE OF THE
> 9-5/8 PRODUCTION CASING.
>
> THIS IS ALL I KNOW AT PRESENT.

Log in or register to leave a comment

lengould on May 4, 2010 - 10:59am Thanks. Excellent information.

Check out the entire discussion at:
http://www.theoildrum.com/node/6430#more

Oil Spill On It's Way

From the Huffington Post:GULFPORT, Miss. — Scientists say the Gulf oil spill could get into the what's called the Loop Current within a day, eventually carrying oil south along the Florida coast and into the Florida Keys.

Nick Shay, a physical oceanographer at the University of Miami Rosenstiel School of Marine and Atmospheric Science, said Monday once the oil enters the Loop Current, it likely will end up in the Keys and continue east into the Gulf Stream.

Shay says the oil could affect Florida's beaches, coral reefs, fisheries and ecosystem within a week.

He described the Loop Current as similar to a "conveyor belt," sweeping around the Gulf, through the Keys and right up the East Coast.

Shay says he cannot think of any scenario where the oil doesn't eventually reach the Florida Keys.

There is nothing further that needs be said, is there? We are ruined if it does land here.